Panels get cast flat on the slab, so the layout has to be right before anyone orders concrete.

Tilt wall looks simple from the road: big concrete panels, straight joints, done. On site, the whole schedule hangs on a layout drawing made weeks earlier.

Panels are cast flat on the building slab, which means the slab has to be poured, cured and clean before casting starts. Every opening, embed and lift insert is located on paper first.

On the lift day, a crane walks the panels up in sequence. Get the sequence wrong and the crane has to reposition, which costs a day you cannot get back.

This is one of the places design-build earns its keep. We are looking at panel joints, openings and lift points while the drawings are still being produced, not after they are stamped.

 

share this

Read next / Field Notes

Assisted Living Design Features That Support Residents and Staff

Related Articles
Assisted Living Design Features That Support Residents and Staff

Field Notes

Assisted Living Design Features That Support Residents and Staff

Assisted living construction should make daily life easier for the
November 9, 2026
Planning a Surgery Center: Systems, Timelines and Construction

Field Notes

Planning a Surgery Center: Systems, Timelines and Construction

A surgery center needs a different kind of plan than
November 9, 2026
A Step-by-Step Guide to Planning a Private School Expansion

Field Notes

A Step-by-Step Guide to Planning a Private School Expansion

A private school expansion is not just about adding classrooms.
November 9, 2026